Nassau Crossing Park in Yulee: What's Open Now

August 20, 2026

Pull up Nassau County's own page for Nassau Crossing Park today and you will find a sentence that says a splash pad is "out to bid" for a construction firm to build it. The splash pad opened to the public on September 26, 2025, at 1 p.m., and it has been running daily from 9 a.m. to 7 p.m. ever since, filtered through a 6,000-gallon recycled water system built to hold up through a Florida summer.

Nassau Crossing is one of several park projects moving through construction, design, or planning around Yulee. This guide brings together what is open and what remains in progress across those projects.

What the county's page still says

As of this writing, Nassau County's Nassau Crossing page describes two things as currently under construction: two irrigated multi-use rectangular fields, and the installation of 63 lights meant to illuminate the walking path. The page also describes other park features.

That framing made sense in 2022, when the park had its grand opening and roughly 150 people showed up for the ribbon cutting. Since then, additional parts of the park have opened.

What you can actually use right now

Here is what has been open and running at Nassau Crossing Park, at 77480 William Burgess Blvd, for months:

  • Two enclosed playgrounds, one scaled for toddlers and one built for older kids, with swings, rock walls, a treehouse, and what the county itself calls Nassau County's tallest slide
  • 2.5 miles of multi-use trails through the park's 57 acres
  • A small dog park with nine agility obstacles, leash posts, waste stations, a water fountain, and a misting fire hydrant for hot afternoons
  • Picnic areas with gazebos, outdoor fitness stations, restrooms, and a community plaza built around a train caboose that nods to the area's railroad history
  • The splash pad, open daily from 9 a.m. to 7 p.m., built by ACON Construction Co. under a contract the county board amended back in early 2025 to cover the rest of the design and build cost

That gives visitors another option alongside the park's trails and playgrounds.

What is still in progress

The two rectangular fields and the 63 path lights are the real remaining pieces, and the county's own language on this part checks out. There is no separate news report confirming a completion date for either, which means the county's "currently under construction" note is the most current information available for those two specific items. If you are planning around night walks or organized field use at Nassau Crossing specifically, that is the piece still in progress.

Why Yulee is building this many parks at once

It can look like the county suddenly decided to build half a dozen parks in the same few years, and in a sense, it did, but the reason has less to do with a sudden windfall of tax revenue and more to do with how Nassau County chose to pay for growth. In January 2021, the county adopted a Parks and Recreation Open Space Master Plan that treats parks the same way it treats roads and utilities, as infrastructure that has to keep pace with new rooftops rather than catch up to them later. The plan's stated goal is a recreation facility within a ten-minute walk of most homes, and the funding behind it leans heavily on impact fees and public-private partnerships rather than a countywide tax increase, meaning developers building new neighborhoods are largely paying to build the parks that serve them.

That is why Nassau Crossing exists at all. It was built through a partnership between the county and Matovina & Associates, the developer behind the neighboring Nassau Crossing community, with construction starting back in September 2019. It is also why several other parks around Yulee are moving through construction phases on similar timelines. The growth is paying for the amenities as it goes.

The rest of the pipeline

Nassau Crossing is the most finished piece of a larger build-out happening across Yulee right now. Here is where the rest of it stands, based on the county's own project descriptions as of August 2026:

Park Status as of August 2026 What comes next
Nassau Crossing Park Playgrounds, trails, dog park, and splash pad open; two fields and 63 path lights still under construction Fields and path lighting are the last major piece
Nassau Station Park 4.3 acres open along William Burgess Blvd Planned expansion to 15.59 acres, with trails linking to Nassau Crossing and the future Liberty Cove
Liberty Cove 13.24 acres and 1.45 miles of riverfront open Planned expansion to 46.14 acres, adding public water access to the Nassau River and its tributaries
Blackrock Cove Park Phase 1 complete Phase 2 currently under design
Tributary Regional Park Phases 1 and 2 complete, with ball fields and a playground Phase 3 construction set to begin in the coming months, with kayak launch facilities under design
Yulee Sports Complex / Eastside Regional Park 128 of an eventual 567.5 acres Phase 1, budgeted at $2.2 million, is under design and will add parking, restrooms, and three FIFA-regulation multi-purpose fields with lighting

The Yulee Sports Complex expansion is worth a closer look on its own. It started at 20 acres in 2021 and has grown to 128 through a public-private partnership, with additional acreage reserved under the county's East Nassau County Planning Area sector plan for an eventual total of 567.5 acres. In February 2026, the county closed on an adjacent parcel at 86067 Pages Dairy Road specifically to keep expanding that footprint. None of the new fields are open yet. The land is being assembled before the fields are built, which is a slower process than it looks from a headline but a more durable one than announcing fields on land the county does not yet control.

What to actually do with this

If you live in Yulee and want to use what is already finished while keeping track of what remains in progress:

  1. Go to Nassau Crossing Park expecting a full amenity list, not a partial one. The splash pad, both playgrounds, the dog park, and the trail system are all running now.
  2. Call Nassau County Parks and Recreation at 904-530-6010 before a special trip if you are trying to time something around field use or path lighting specifically, since those two pieces are the ones still genuinely in progress.
  3. Watch William Burgess Boulevard for the next visible change. Nassau Station Park's planned expansion and Liberty Cove's build-out are both designed to connect back to Nassau Crossing by trail, so this corridor is where the next round of ribbon cuttings is likely to happen first.

For updates on the other park projects in the pipeline, contact Nassau County Parks and Recreation before making a special trip.